Project overview

Roof-mounted solar with battery storage and a hybrid inverter, sized to the home real daily consumption.

We sized a roof array against twelve months of real consumption data rather than the available roof area. The result covers daytime load, charges a battery for the evening peak and still leaves a clean path back to grid supply.

Work began with a structural check and a shading study across the four seasons. Panels were mounted on a ballasted rail system, with DC cabling routed through a protected riser to a hybrid inverter installed beside the existing distribution board.

Battery storage sits on the cool side of the utility area, its own circuit separated from general household load. A monitoring gateway exposes production, consumption and export in one view, and the system fails over to grid without interruption.

Commissioning included insulation resistance and earth continuity tests, an anti-islanding check, and a handover walkthrough of the monitoring app and shutdown sequence.