Generator Installation

Generator Installation

February 14, 2026 Commercial Electrical
Client Marlow Guest House
Duration 05 Weeks
Service Commercial Electrical
Date February 14, 2026

Project overview

Ensure uninterrupted power during outages with a correctly sized standby generator and changeover.

A guest house could not lose heating, water or corridor lighting during an outage. The standby system restores essential circuits within seconds.

Load was split into essential and non-essential groups, and the generator was sized against the essential group with headroom for starting loads. An automatic transfer switch sits between the mains intake and the essential distribution board.

The set was installed on a levelled plinth with a weatherproof enclosure, fuel isolation and an acoustic canopy that keeps noise inside the site boundary.

Commissioning covered a full load-bank test, a simulated outage with timed transfer, and a written monthly test routine for the site team.